The Jiwa Manufacturing Module is a fairly comprehensive system but at it's most basic can be used simply as a Bill of Materials and Works Order facility. The advanced features are optional and would most likely only be used by organisations who run a larger and more complicated manufacturing facility.

The Bill of Materials facility has unlimited levels which means a bill can contain one or more sub assemblies which in turn can contain more sub assemblies

 

This is the Bill of Materials Screen. In this mode it is showing the stages, inputs (raw materials and sub assemblies) and outputs (finished Goods). Each stage is performed within a work centre and is associated with one or more raw materials / sub assemblies.. Stages are optional and would not be used for a simple build. 

 

JiwaManufacturing01.png

The Works Order explodes the production quantity by the bill quantities. A works order has multiple statuses (e.g. "not started", "in progress", "on hold", "finished", etc)

 

JiwaManufacturing02.png

 

Bills and works orders also have the ability to have multiple input options and multiple outputs.

 

JiwaManufacturing03.png

 

You can define Work Centres with associated skill requirements

 

JiwaManufacturing04.png

Skills are defined within the Human Resources area.

 

JiwaManufacturing05.png

Each employee can have one or more skills associated with them.

 

JiwaManufacturing06.png

Production areas define Production Lines and their associated work centres. 

 

JiwaManufacturing07.png

You can define one or more shifts and also define the capacity that shift has within each work centre. 

 

JiwaManufacturing08.png

The system has a comprehensive scheduling facility with a colour coded Gantt chart of all works orders. The system tracks each day and works out the capacity on each work centre. When a work centre has more work scheduled that it is able to handle, it highlights that day in red and also shows you the corresponding work center capacity below

 

JiwaManufacturing09.png

 

The following is a short video showing you through the Jiwa Manufacturing and Bill of Materials facility:

 

 

This video is best seen on the full screen. Just click on the icon at the bottom right of the video (see image below).

To exit full screen just press escape 

 

VideoFullScreen.jpg

Was this article helpful?
0 out of 0 found this helpful
Have more questions? Submit a request

Comments

This entire document, including design, text, videos,graphics, and photographs are Copyright © 2014 Austlink Plus Pty Ltd, All Rights Reserved.
No part of this document may be reproduced in any way or by any means for commercial or any other purposes, without prior written permission of Austlink Plus Pty Ltd. Use of any data for the purpose of creating promotional materials or producing a printed or electronic catalog of any kind is expressly forbidden without prior written permission of Austlink Plus Pty Ltd.

Powered by Zendesk